Clementine

Project

Clementine

Client

Satterley Property Group

Consulting Engineer

Cossill & Webley Consulting Engineers

Wormall Civil Project Management

James Boggan

Wormall Civil Site Supervision

Sean Glover

Project Duration

Description

Wormall Civil started the Bulk Earthworks for Stage 1 in February 2020, this work followed through to the civil works starting with practical completion awarded in November 2020.

December 2020 saw the bulk earthworks starting in Stage 2, with the civil works starting the following February. Successful practical completion was achieved for this Stage in October 2021.

With works being carried out in Stage 2, the project team also started the upgrades to both Apple Street and Orange Avenue in early 2021 (these works are currently ongoing with practical completion planned for later this year).

As well as the upgrade works to these roads, Wormall Civil were also contracted to install a section of pressure main for the Water Corporation as part of the new sewer infrastructure from Bullsbrook to Ellenbrook.

Summer 2021- 2022 will continue to be busy on the project with the bulk earthworks to Stage 6, 7 & 8 as well as the civil works to Stage 3 & 6 planned to start with practical completion expected in early 2022.

Below is an overview of the projects statistics to date:

  • Clearing: 143,345m2
  • Import Fill Sand: 331,047 tonnes
  • Sewer Reticulation: 2.8 km’s
  • Drainage Installation: 3.2 km’s
  • Water & Gas: 2.8 km’s
  • Retaining Walls: 2.8 km’s
  • Road Construction: 34,646 m2
  • Footpaths: 2,386 m2
  • Kerbing installation: 3.5 km’s