Golden Bay

Project

Golden Bay

Client

Peet and Development WA

Consulting Engineer

Cossill & Webley Consulting Engineers

Wormall Civil Project Management

Catherine Cunningham

Wormall Civil Site Supervision

Sam McKersey

Project Duration

Description

Multiple stages running between bulk earthworks, civils and pump station installation.

Stage 5G bulk earthworks saw cut to fill of approximately 105,000m3 with approximately 50,000m3 to be exported off site.

Stage 4E included cut to fill of approximately 40,000m3. Prior to any bulk earthworks project at Golden Bay Fauna Trapping Specialists are engaged to trap and relocate the local fauna. The specialists stay on site for the duration of the clearing works to ensure all fauna are safely relocated from the works area.

Over the last 12 months stage 5c, 4J and 5D civils works have been completed – 130 lots. During this time 2 waste water pump stations have also been installed.