Kingston Estate, Australind
Project
Kingston Estate, Australind
Client
Australian Vanguard Pty Ltd
Consulting Engineer
Kotula Civil
Wormall Civil Project Management
Tinus Spangenberg
Wormall Civil Site Supervision
Jarrad Tiltman
Project Duration
September 2020 - February 2021
Description
Wormall Civil have completed 2 stages at Kingston Estate.
Work in these stages included topsoil strip, import fill, sewer network, drainage, water and gas, power and communication networks. It also included the establishment of batter to the foreshore along Oakridge Rd.