Florence Estate

Project

Florence Estate

Client

Satterley Property Group

Consulting Engineer

Peritas Consulting – Oleg Omelchuk

Wormall Civil Project Management

Wormall Civil Site Supervision

Brent Walker

Project Duration

Late 2021 – ongoing

Description

Residential development is adjacent to Kwinana Freeway with 111 lots completed so far and 132 lots under construction slated to be completed by late 2023.

Scope included:

  • 160,000 m3 od sand cut to fill
  • 500mm of deep sewer up to 6m deep
  • 1380m of gravity sewer
  • 1650m of Roadworks
  • 600m of up to 5m tall precast Noise Wall ( Completed by PC Walls, We only provided earthworks and excavations/backfill for the wall )
  • 1900m of limestone retaining wall