Spindrift Stage 1

Project

Spindrift Stage 1

Client

Goldfields Margaret River Pty Ltd

Consulting Engineer

Stantec/JDSi

Wormall Civil Project Management

Tinus Spangenberg

Wormall Civil Site Supervision

Arthur Ruedi/ Jamie Strickland

Project Duration

Ongoing

Description

Spindrift is a modern and meticulously designed neighbourhood located in Margaret River. Spindrift is home to all the conveniences you’d expect from a modern estate, including impressive natural landscapes and immediate access to neighbouring parks and playgrounds, with schools, shops, cafes, restaurants and medical facilities all within easy reach.

Wormall Civil are proud to be working on Stage 1, which is a 70-lot subdivision. Wormall Civil are currently performing the below works on the project:

  • 71000m2 clearing and topsoil strip
  • 2016m sewer up to 4m deep
  • 2400m drainage pipe installation up to 900mm diameter
  • 1980m of subsoil
  • 2690m water pipe installation
  • 9650m2 roads with black and red asphalt with 150m2 paving
  • 1257m footpaths 2m wide
  • 4976m power cabling with associated domes
  • Transformer
  • 27 streetlights

Wormall Civil would like to thank Survcon who supplied images for this project.