Wormall Civil is delighted to have completed the civil construction work on Kudardup Heights Stage 3A, B, C

Name of Project: Kudardup Heights Stages 3A,B,C 

Consulting Engineer:  WML Consulting Engineers 

Client:  Kudardup Village Pty Ltd 

Wormall Civil Project Manager:  Tinus Spangenberg 

Wormall Civil Site Supervisor:  Bryce Wills 

Wormall Civil is proud to commencing the civil construction work on Kudardup Heights Stage 3A, B, C. Located south of Margaret River and less than 5 minutes from Augusta it is surrounded by the perfect combination of nature and community to create the ultimate lifestyle.  

Kudardup is a master planned village taking full advantage of the abundant natural features and rural setting to provide a mix of cottage, rural living and lifestyle options. 

Wormall Civil have completed three stages of Kudardup Heights simultaneously comprising of the following works: 

  • 845m drainage pipe up to 525 diameter 
  • 1555m subsoil 
  • 6170m2 asphalt including cross overs into lots, 3350m2 asphalt overlay on Kudardup Road 
  • 1900m of kerb 
  • Power install including transformer and NBN installation 

Learn more about Wormall Civil capabilities here