Cape Rise Estate, Dunsborough

Project

Cape Rise Estate, Dunsborough

Client

Andrew & John d'Espeissis

Consulting Engineer

WML Consultants

Wormall Civil Project Management

Tinus Spangenberg

Wormall Civil Site Supervision

Graham Broom

Project Duration

August 2020 - January 2021

Description

Cape Rise stage 1 providing 18 lots consisted of the following:

  • 16,000m3 imported fill
  • 570m of limestone retaining wall
  • 280m of drainage pipe with pits and 800m of subsoil drainage
  • Culvert under access road to accommodate existing stream flow
  • 4500m2 red and black asphalt with 600m of concrete footpath
  • 650m of water main
  • Electrical power supply and streetlights along with communication network
  • Bore under Cape Naturaliste Drive to connect sewer to existing outfall