Davis Road Waste Facility
Project
Davis Road Waste Facility, Witchcliffe
Client
Shire of Augusta Margaret River
Consulting Engineer
WML
Wormall Civil Project Management
Warwick Kindt
Wormall Civil Site Supervision
Project Duration
October 2020 - January 2021
Description
This project included construction of a new poly lined effluent pond & a new waste Cell 3. Cut to fill earthwork were carried out in an old gravel pit immediately adjacent to the existing waste facility to construct the leachate pond.
Once the pond was plastic lined and signed off by the regulator, effluent from Councils existing ponds could be transferred, allowing de-sludging of the existing clay ponds and construction of a geo-clay lined new cell who’s footprint incorporated the previous redundant effluent ponds.
Work was completed over 2 summer construction periods.