One71 Stage 4
Project
One71 Stage 4
Client
Mirvac
Consulting Engineer
DEC
Wormall Civil Project Management
Joshua Gibb
Wormall Civil Site Supervision
Chris Nelson
Project Duration
November 2022 - October 2023
Description
One71 Baldivis is surrounded by existing amenity with easy access to the Kwinana Freeway and only a short 3-minute drive from the Baldivis Shopping Centre.
Living in Baldivis means you are walking distance to the new Sheoak Grove Primary School, only 10 minutes from Rockingham beach and 30 minutes south of Perth.
Wormall Civil are proud to undertake the below works:
- Import limestone, Ground improvement works – 24,928.0m3
- Import Clean Fill – 78,700m3
- Sewer – 2-3m, 252m 3-4m 344.7m
- Drainage 0-2m 1336.70, 2-3m 100m Ranging from 300mm – 700mm Pipe Dia
- Water & Gas 100mm Water 629.3 M 100mm, same as 63mm gas mains
- Underground Power 715m Transformer installer
- Comms 1049m Conduit
- Roads,5755 m2 Subgrade, Limestone & Road base Construction
- Kerbs 1330 m
- Footpaths 1880m2
- Asphalt 3950m2