Project

Parkridge Estate, Eaton

Client

Parkridge Group (2017) Pty Ltd

Consulting Engineer

Edgeloe Engineering

Wormall Civil Project Management

Tinus Spangenberg

Wormall Civil Site Supervision

Jarrad Tiltman

Project Duration

October 2021 - April 2021

Description

Parkridge Stage 2A and 2B providing 32 lots consisted of the following:

  • 38,000m3 imported fill
  • 590m sewer network
  • 525m of limestone retaining wall
  • 425m of drainage pipe with pits and swales
  • 3200m2 red and black asphalt with 260m of concrete footpath in grey
  • 500m of water main
  • Electrical power supply and streetlights with transformer along with communication network