The Avenue Stage 10A

Project

The Avenue Stage 10A

Client

PEET

Consulting Engineer

Cossill & Webley

Wormall Civil Project Management

Justin Fitzpatrick

Wormall Civil Site Supervision

Craig Bennett

Project Duration

Ongoing

Description

The Avenue Stage 10A is a bulk earthwork and civil contract with PEET. Conveniently located next to Tonkin Highway and Rowley Road in the growing suburb of Hilbert.

Wormall Civil are proud to have Stage 10A on track to be completed early November.

Project scope entails

  • Clay grading across the stage
  • Approx 60,000m3 Import Fill
  • 800m Sewer Reticulation
  • 1120m Stormwater and Subsoil
  • 350m Water and Gas Reticulation
  • 1700m of Power installation and streetlighting with transformer, along with 740m of Communication Installation
  • 3200m2 Asphalt
  • 400m Footpath and 650m of kerbing

 