The Avenue Stage 10A
Project
The Avenue Stage 10A
Client
PEET
Consulting Engineer
Cossill & Webley
Wormall Civil Project Management
Justin Fitzpatrick
Wormall Civil Site Supervision
Craig Bennett
Project Duration
Ongoing
Description
The Avenue Stage 10A is a bulk earthwork and civil contract with PEET. Conveniently located next to Tonkin Highway and Rowley Road in the growing suburb of Hilbert.
Wormall Civil are proud to have Stage 10A on track to be completed early November.
Project scope entails
- Clay grading across the stage
- Approx 60,000m3 Import Fill
- 800m Sewer Reticulation
- 1120m Stormwater and Subsoil
- 350m Water and Gas Reticulation
- 1700m of Power installation and streetlighting with transformer, along with 740m of Communication Installation
- 3200m2 Asphalt
- 400m Footpath and 650m of kerbing